Carson Road Report: Roundabout work continues as part of South Carson Street project
Here is the South Carson Street Project and Carson City area road report for the week of July 6-12, 2020. For information on lane restrictions and street closures related to the South Carson Street Project, please visit CarsonProud.com.
South Carson Street Project
SNC crews are preparing the roundabout installment phase of the project. The Construction Map has been updated to reflect July 6-10 cone zone.
— 5th Street to Stewart St: one lane in each direction will be open, the cone zone will remain in place around-the-clock.
— 9th Street will be closed Monday, July 6.
— Stewart Street will remain closed with detours on Fairview, Little, and Roop.
— Frontage Road is open to two - way traffic with a north driveway closure.
— Colorado Street will be closed on Friday July 10.
— Fairview Drive: one lane in each direction will be open around-the-clock. Driveway closures as needed.
— Fairview to Appion: one lane in each direction, the cone zone will remain in place around-the-clock.
Carson City Road Report
Closures are expected at the following locations due to road, utility work:
— Airport Road remains closed in both directions between Woodside Drive and Menlo Drive for installation of new sewer and water utilities. Airport Road will also be closed in the southbound direction only between US 50 and Woodside Drive, Monday through Friday, all day. Northbound Airport Road will remain open. Residential and business access will also be allowed. JAC service will continue; however, detours will be in effect.
— Livermore Lane and the Pete Livermore Sports Complex will be closed until further notice while the parking lot is reconstructed.
— Retail Court will be closed east of College Parkway, Monday through Friday, all day. Access to the businesses will be maintained. There may also be periodic closures and detours to the multi-use path between Emerson Drive and Retail Court.
— Robinson Street will be closed beginning at Saliman Road and continuing to the east along the high school, Monday through Friday, 7:00 am to 5:00 pm. Access for school buses will be allowed.
Lane restrictions are expected at the following locations due to road/utility work:
— 5th Street will have single lane closures and lane shifts between Stewart Street and Roop Street for utility work, Wednesday, 7:00 am to 5:00 pm.
— College Parkway will have a single lane closure in the westbound direction between the I-580 Interchange and Retail Court for construction associated with the adjacent development, Monday through Friday, 9:00 am to 3:00 pm. The lane closure will extend up the interchange off-ramps.
— Fairview Drive will have continued eastbound and westbound single lane closures while utility work and roadway reconstruction occurs, Monday through Friday, 7:00 am to 5:30 pm.